Stettler Downtown Streetscape

PROJECT. Downtown Streetscape

LOCATION.  Stettler, AB

OWNER. Town of Stettler

OWNER’S REPRESENTATIVE.

Melissa Robbins C.E.T, Director of

Operational Services  

mrobbins@stettler.net

START DATE.  Phase 1 - 2010

COMPLETION DATE.  Phase 2 - 2012

CONSTRUCTION COST. $800,000

TAGISH’S ROLE.  Prime Consultant

 

PROJECT DESCRIPTION.

Downtown Streetscape and Road Reconstruction, project consists of removing and replacing all of the existing concrete sidewalks, curbs and gutters and paved surfaces. The existing concrete /paving stone sidewalks were replaced with traffic calming with Allen Block planters and benches at ends and midpoints of each block and sidewalk replacements that consist of an elaborate train track design. The results are an aesthetic street that provides pedestrians areas to relax and converse.

 

CONSTRUCTION HIGHLIGHTS.

  • Remove and Replace Standard Curb and Gutter                     

  • Remove and Replace Asphaltic Concrete Pavement              

  • Supply & Install Railroad Track Concrete Sidewalk                 

  • Supply & Install Standard Broom Finished Sidewalk               

  • Supply & Install Median Concrete Exposed, Agg                      

  • Supply and Install Allan Block Wall                                             

  • Supply and Install 914mm Tree Grates                                       

  • Supply and Install R-7582 Reliance Bollards                            

  • Construction Observation and Inspection

     

     

     

     

     

     

     

     

     

                                   

SERVICES PROVIDED.

  • Project Scope Definition and Preliminary Design

  • Detailed Engineering Design

  • Tender Preparation

  • Project Management & Contract Administration

  • Overall site design

 