© 2016 Tagish Engineering Ltd.

  • LinkedIn - Grey Circle
  • Google+ - Grey Circle

Meadowlands by the Park

PROJECT. Meadowlands by the Park

LOCATION.  Stettler, AB

OWNER.  Mittleland Developments

OWNER’S REPRESENTATIVE.

Mike Dandurand

buyabiz@shawbiz.ca

 

START DATE.  2007

COMPLETION DATE.  2009

CONSTRUCTION COST.  $2.6 Million

TAGISH’S ROLE.  Prime Consultant

 

PROJECT DESCRIPTION.

Tagish Engineering was commissioned to manage the development of Meadowlands by the Park, a three phase residential development in Stettler, AB. The first phase alone included stripping and grading of the subject property which included the creation of 17 walkout residential home lots adjacent to the Town's new recreational sports park, tendering and the installation of over 700 lineal metres of storm, sanitary and water mains, the extensions of the Towns sanitary and water trunk mains, road and lane construction, including curb and gutter installations. Tagish Engineering also was the shallow utility coordinator, in relation to all natural gas, cable TV, phone and electrical installations.

 

ENGINEERING/C HIGHLIGHTS.

  • 700m of Sanitary, Storm and Water line installation

  • 1300m of Curb/Gutter installation and roadway construction

  • Power, natural gas, cable TV and phone servicing

  • 700m of Sanitary Trunk Main installation and connection to existing Town services

  • 400m of Water Trunk Main installation and connection to existing Town services

     

1/3

CONSTRUCTION HIGHLIGHTS.

  • Preliminary Engineering and Cost Estimating      

  • Detailed Design and Tender Preparation of Phase 1 Infrastructure

  • Project Management and Contract Administration                         

  • Obtaining proper provincial and municipal approvals

  • Detailed preliminary site and construction layout surveys

  • Overseeing 3rd party contractors for

    • Construction

    • Servicing

  • Construction Observation

     

     

     

     

     

     

     

     

  •