Horn Hill Waste Transfer Road Rehabilitation

PROJECT. Horn Hill Waste Transfer Road Rehabilitation

LOCATION.  Hwy 42 Horn Hill

OWNER. Red Deer County

OWNER’S REPRESENTATIVE.

Rob Mayhew – Engineering Manager

rmayhew@rdcounty.ca

START DATE.  October, 2015

COMPLETION DATE.  October, 2015

CONSTRUCTION COST.  $56,000

TAGISH’S ROLE.  Prime Consultant

 

PROJECT DESCRIPTION.

Tagish Engineering was commissioned to assess and design remediation for the failure of an internal road at the Horn Hill Waste Transfer Site

                                             

 

ENGINEERING HIGHLIGHTS.

•   Assessment and design to reconstruct the internal road

•   Site drainage design to alleviate the effects of high water table on the road structure

•   Drainage improvements, road re-structuring and triaxle re-enforcement geogrid application

 

CONSTRUCTION HIGHLIGHTS.

  • Project Management

  • Construction Observation and Inspection

  • Dealing with flowing underground spring activity

  • Field design of perforated piping drainage system

     

     

     

     

     

     

     

     

     

SERVICES PROVIDED.

  • Preliminary Survey

  • Assessment of the problem and innovative design to alleviate road failure

  • Tender and Contract

  • Contract Administration

  • Project Management

  • Construction Observation and Inspection

 

 